Model and Practice Questions of Quantitative Aptitude for Bank Exams

TIME AND WORK
1.    If A can do a piece of work in n days, work done by A in 1 day = 1/n.
2.    If  A does 1/n work in a day, A can finish the work in n days
    If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day (where all men work at the same rate), then
    M1 D1 H1W2 = M2 D2 H2 W1    
    If A can do a piece of work in p days and B can do the same in q days, A and B together can finish 

    it in pq+(p+q) days
    If A is thrice as good as B in work, then
    Ratio of work done by A and B 
= 3 : 1
    Ratio of time taken to finish a work by A and B = 1 : 3
Additional 600+ Seats Available for NEET UG Round 2 Counselling 2024!
Practice questions
1.    A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days, how many days will B take to complete the task if he works alone?
    1) 9 days    2) 7 days    3) 5 days
    4) 3 days    5) None of these
2.    A and B together can complete a particular task in 8 days. If B alone can complete the same task in 10 days, how many days will A take to complete the task if he works alone?
    1) 28    2) 36    3) 40
    4) 32    5) None of these
3.    A and B together can complete a particular task in 6 days. If A alone can complete the same task in 10 days, how many days will B take to complete the task if he works alone?
    1) 15    2) 16    3) 14
    4) 12    5) None of these
4.    A and B together can complete a particular task in 4 days. If A alone can complete the same task in 6 days, how many days will B take to complete the task if he work alone?
    1) 8    2) 17    3) 14
    4) 12    5) None of these
5.    Yesterday Priti typed an essay of 5000 words at the speed of 60 words per minute. Today she typed the same essay faster and her speed was 15 % more than yesterday. What is the approximate difference in the time she took to type yesterday and the time she took to type today?
    1) 20 min    2) 30 min    3) 10 min    4) 40 min    5) 1 hour
SBIF Asha Scholarship Program for School Students| Scholarship Amount Rs.15,000/-
6.    Yesterday Shweta completed 300 units of work at the rate of 15 units per minute. Today she completed the same units of work but her speed was 40% faster than yesterday. What is the approximate difference in the time she took today?
    1) 16 min    2) 26 min    3) 46 min    4) 36 min    5) 6 min
7.    12 men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
    1) 18    2) 12    3) 24
    4) Cannot be determined
    5) None of the above
8.    18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?
    1) 9    2) 6    3) 12
    4) 8    5) None of these
9.    24 men can complete a piece of work in 15 days. In how many days will 18 men complete that work?
    1) 16 days     2) 20 days
    3) 22 days    4) 25 days
    5) None of these
10.    22 Men can complete a job in 16 days. In how many days will 32 Men complete that job?
    1) 14    2) 12    3) 16
    4) 9    5) None of these
Telangana DSC 2024 Final Key Released: Download SGT and SA Question Papers with Key
11.    10 Men can complete a piece of work in 8 days. In how many days can 16 men complete that work?
    1) 4 days    2) 5 days    3) 6 days
    4) 3 days    5) None of these
12.    16 Men can complete a piece of work in 7 days. In how many days will 28 men complete the same work?
    1) 6 days    2) 8 days    3) 3 days
    4) 4 days    5) None of these
13.    A alone can make 100 baskets in 6 days and B alone can make 100 baskets in 12 days. In how many days can A and B together make 100 baskets?
    1) 3 days    2) 5 days
    3) 21/2 days    4) 31/2 days
    5) None of these
14.    A single person takes 8 minutes to type a page. If from 1.00 pm to 2.00 pm, 1710 pages are to be typed, how many persons should be employed on this job?
    1) 207    2) 221    3) 249
    4) 256    5) None of these
15.    A single person takes 3 min to write a letter. If from 10 am to 12:00 noon, 1960 letters are to be written, how many persons should be employed on this job?
    1) 53    2) 47    3) 51
    4) 49    5) None of these
New Medical Colleges 2024: Permissions Granted for Pulivendula and Paderu Medical Colleges
Key with Solutions

1.    Ans: 5
    Sol: Given, A and B can complete a task in 4 days.
    Therefore, work done by (A+B) 
    in 1 day = 1/4 
    Work done by A alone in 1 day =1/12
    Therefore, work done by B alone in 1 day = 1/6
    Hence, B alone can complete the work in 6 days.
2.    Ans: 3
    Sol: Given, A and B can complete a task in 8 days.
    Therefore, work done by (A+B) 
    in 1 day =1/8
    Work done by B alone in 1 day
    =1/10
    Therefore, work done by A alone in 1 day =1/40
    Hence, A alone can complete the work in 40 days.
3.    Ans: 1
    Sol: Given, A and B can complete a task in 6 days.
    Therefore, work done by (A+B) 
    in 1 day =1/6
    Work done by A alone in 1 day
    =1/10
    Therefore, work done by B alone in 1 day = 1/15
    Hence, B alone can complete the work in 15 days.
4.    Ans: 4
    Sol: Given, A and B can complete a task in 4 days.
    Therefore, work done by (A+B) 
    in 1 day =1/4
    Work done by A alone in 1 day=1/6
    Therefore, work done by A alone in 1 day =1/12
    Hence, B take 12 days to complete the work.
5.    Ans: 3
    Sol: The time took to type yesterday = 83.33 min
    Priti's speed of typing today = 60 words per min + 15% of 60 words per min
    = 60 + 9 = 69 words per min
    The time took to type today
    = 72.46 min.
     Required difference = 83.33 – 72.46 » 10 min
English Grammar Model Questions for Bank Exams
6.    Ans:
5
    Sol: The time she taken to complete the work yesterday = 300/15 = 20 min.
    The rate of work done by sweta today = rate of yesterday + 40% of rate of yesterday
    = 15 + 6 = 21 units per min
    The time she taken to complete 

    the work today = 300/21 = 14.2 min.
     The required difference 
    = 20 – 14. 2 » 6 min 
7.    Ans: 1
    18 days
8.    Ans: 1
    Sol: 12 days work of 18 women = 9 days work of 12 men
    18 × 12 women = 9 × 12 men
    2 women = 1 man
    8 men + 8 women = 8 men
    + 8/2 men= 8men + 4 men= 12men
    So, 8 men + 8 women or 12 men can do the work in 9 days. (according to the question)
9.    Ans: 2
    Sol: Let 18 men can complete the same work in x days, then
    18 : 24 :: 15 : x
    18 × x = 24 × 15
    x= 20 days
10.    Ans: 5
    Sol: Let 32 men can complete the same work in x days, then
    32 : 22 :: 16 : x
    32 × x = 22 × 16
    x= 11 days
Another Telangana DSC with 6,000 Teacher Posts Soon: Bhatti Vikramarka
11.    Ans:
2
Sol: Let 16 men can complete the same work in x days, then
    16 : 10 :: 8 : x
    16 × x = 10 × 8
    x= 5 days
12.    Ans: 4
    Sol: Let 28 men can complete the same work in x days, then
    28 : 16 :: 7 : x
    28 × x = 16 × 7
    x = 4 days
13.    Ans: 5
    Sol: If A can do a work in x days and B can do the same work in y days, then both of them together 
    complete that work in xy/(x+y) days
    = 4 days
14.    Ans: 5
    Sol: In 1 hour (60 min) 
    60/8 pages written by 1 man
     1 page written by 8/60 
    1710 pages written by
     = 228 men
15.    Ans: 4
    Sol: In 2 hours (120 min)
    120/3 = 40  letters written by 1 man
    40 letters written by 1 man
        1 letter written by 1/40 
     1960 letters written by
    (1/40)×1960 - 49 men